Rules by state

Solar and battery interconnection rules in PR

Puerto Rico net metering statute and interconnection regulation. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities, municipal utilities, electric cooperatives, other utilities.

Check a PR address free
How the size is measured: not published

The published limits here are stated in kilowatts without saying whether that is the inverter rating in alternating current or the array rating in direct current. On a system near a threshold that decides which band it lands in, so the checker asks the question rather than choosing an answer.

The screens that decide it

Ask the utility this, before you sell it

  1. Is there a distinct net metering eligibility cap separate from the interconnection technical limit? The materials read did not distinguish the two.

Worth knowing before you quote

Net metering for a new customer today is full retail, the same as a legacy customer, and is not scheduled to move to a lower net billing credit: Act 10-2024 bars the Puerto Rico Energy Bureau from restudying the program before January 2030 at the earliest, with any resulting change taking effect no sooner than twelve months after the Bureau acts. That lock is itself being challenged in court by the island’s Financial Oversight and Management Board, so treat the current program as durable rather than permanently settled. The consolidated interconnection regulation covers any generating facility or microgrid seeking to interconnect, excluding only islanded systems, and replaced two prior PREPA regulations that used to be split by distribution versus transmission level. Puerto Rico has no counties; permit offices in this platform are seeded one per municipio, the Census Bureau’s county equivalent for the territory, and which municipios hold independent permitting authority versus route through the central permitting office, OGPe, has not been confirmed. Ask the specific municipio which applies before assuming either way.

Utility programs we have read in PR

Source

Puerto Rico net metering statute, 22 L.P.R.A. section 1014, as amended by Act 10-2024, with the Puerto Rico Energy Bureau consolidated Generating Facility and Microgrid Interconnection Regulation, docket NEPR-MI-2019-0009, Resolution and Order of 15 July 2021

Read and recorded 2026-09-12. This regulation binds interconnection territory wide under Puerto Rico Energy Bureau oversight rather than under a state public utilities commission, and would bind any future second utility. Today LUMA Energy is the sole transmission and distribution operator for the entire territory, so this layer and LUMA’s own program describe one grid in practice. The consolidated regulation replaced prior PREPA Regulations 8915 and 8916. Act 10-2024’s text and the docket’s own filings returned corrupted to automated retrieval during this research; the findings below are corroborated by the Financial Oversight and Management Board’s own public FAQ and by the Board’s July 2024 lawsuit challenging the same law, which confirms its operative effect, but a verbatim quote from the primary text has not yet been captured.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.