Cleveland Public Power small generation interconnection

Their own published program, read and recorded. This outranks the Ohio state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured: not published

The published limits here are stated in kilowatts without saying whether that is the inverter rating in alternating current or the array rating in direct current. On a system near a threshold that decides which band it lands in, so the checker asks the question rather than choosing an answer.

Size bands and what each one obliges

Certified inverter based, 10 kW and under Size 0 to 10 kW

The application fee is currently being waived. Liability insurance is expressly not required, and Cleveland Public Power says so in writing. No standby power charge applies at or below 10 kW of any generation type.

  • Utility accessible disconnect or lock box; a molded case circuit breaker does not satisfy this
  • Local wiring inspector certification and certificate of completion
  • Commissioner signature on Part 2 before energizing
Above 10 kW to 1,000 kW per premises Size 10.001 to 1000 kW

The application fee is currently being waived at this tier too. Solar and wind are exempt from the standby charge at any size, but other generation above 10 kW at a single premises is subject to the standby rate multiplied by the rated capacity, so a solar plus generator job needs the non solar capacity screened separately.

  • Utility accessible disconnect or lock box
  • Payment of the utility’s cost to review the application and perform any necessary studies, at cost

The screens that decide it

Ask the utility this, before you sell it

  1. Is the application fee still waived? The published text waives an existing fee rather than saying none exists, so it can be reinstated without a document revision.
  2. What is the peak load of this line segment and how is it measured? The ordinance names the denominator but not the method.
  3. How long will review and permission to operate take? No timeline is published at any step.
  4. Does the 1,000 kW premises limit refer to the inverter AC rating or the DC source rating? The ordinance never says and the form collects both.

Worth knowing before you quote

Liability insurance is expressly not required, which is the cleanest published statement of that in the platform. Net metering is open and credits are in kilowatt hours rather than dollars, carried over to offset later months until service terminates, at which point any remaining balance is zeroed with no liability to the utility. There is no annual true up and no cash payment ever, which is a material disclosure at the sale of a home. No percentage of consumption cap and no transformer cap are published. For Level 1 review projects the witness test is deemed waived if the utility does not inspect within ten business days after a ten business day minimum notice period, although the documents never define Level 1 by kilowatts. Operational testing before the signed Part 2 may not exceed two hours. Any change to the contractor, inverter manufacturer or model, or system size after the request is deemed complete requires a brand new interconnection request. The installer may run the application as the customer’s recognized agent.

Source

Cleveland Public Power Procedure for Customers to Interconnect Small Generation dated 11 November 2020, reprinting Cleveland Codified Ordinances 523.25 and 523.26 under Ordinance 1662-09 effective 9 December 2009, with the Interconnection Application and Agreement updated 28 November 2022

Read and recorded 2026-09-12. Municipal or public power utility, outside its state's interconnection rule. Its own published documents govern. An Ohio municipal utility. Ohio has no statewide interconnection standard reaching municipals, so the city ordinance is the governing law.

All Ohio interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.