Rules by state · Missouri

Independence Power and Light net metering, Schedule NM-1

Their own published program, read and recorded. This outranks the Missouri state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

the manufacturer nameplate AC power rating in kW. The application form is the only place Independence commits to a unit; the schedule itself states its 100 kW limit twice and never qualifies it as AC, DC or kVA.

Size bands and what each one obliges

100 kW or less, one tier for every size Size 0 to 100 kW

There is no small system tier. A four kilowatt residential job carries the same $100,000 liability insurance requirement, the same annual anti islanding self test and the same 90 calendar day review as a 100 kW commercial one. No application fee or study deposit is published, and a pure ownership transfer with no system change carries no fee at all.

  • $100,000 liability insurance, which may be an existing policy or an endorsement, with no small system exemption
  • Annual anti islanding test, with results produced within 30 days of a request or the utility may disconnect immediately
  • Outdoor manual utility accessible lockable disconnect, satisfied by an inverter with an integral visible lockable accessible disconnect

The screens that decide it

Ask the utility this, before you sell it

  1. How much of the one tenth of one percent program cap remains? Nothing is published and the cap is small enough that it may already be closed.
  2. Request the not to exceed cost statement for interconnection. The schedule expressly requires the utility to provide one on request, and it is the only way to bound the at cost exposure before quoting.
  3. What are the current avoided cost rates? The published 2.51 cents on peak and 2.64 cents off peak are from the sheet effective 1 May 2018 and are recalculated every April by a published formula.

Worth knowing before you quote

This is not a one for one retail credit, despite what secondary sources report. Within a billing period netting is one for one, but any monthly surplus is bought at the average avoided power supply energy cost, published at 2.51 cents per kWh from May through September and 2.64 cents from October through April, itemized on the current month’s bill with no banking, no carryover and no annual true up. Note that off peak pays more than on peak, which is unusual and worth verifying against a current posting. Minimum bill charges and demand charges still apply in any month the customer is a net exporter. The published clocks are in calendar days: approval or denial within 90 days for every size, interconnection within 15 days of a complete application where service already exists, and 15 days for an ownership transfer with no changes. No fifteen percent screen and no minimum load test are published. Interconnection costs are limited to costs that would not have been incurred in serving the customer purely as a consumer, which is a real limit worth invoking.

Source

Independence Power and Light Schedule NM-1 Customer Generator Net Metering Contract Service Rider under Ordinances 17184 and 17248, sheets effective 1 July 2012 with the avoided cost sheet effective 1 May 2018

Read and recorded 2026-09-12. Municipal or public power utility, outside its state's interconnection rule. Its own published documents govern. A Missouri municipal utility. Note that Independence did not adopt the ten kilowatt small system tier that Missouri statute and City Utilities of Springfield both use, so there is no reduced requirement class here at all.

All Missouri interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.