Solar and battery interconnection rules in West Virginia

West Virginia net metering and interconnection. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities, municipal utilities, electric cooperatives.

Check a West Virginia address free
How the size is measured: not published

The published limits here are stated in kilowatts without saying whether that is the inverter rating in alternating current or the array rating in direct current. On a system near a threshold that decides which band it lands in, so the checker asks the question rather than choosing an answer.

Size bands and what each one obliges

Residential, up to 25 kW Size 0 to 25 kW

Nameplate capacity not greater than 25 kilowatts for a residential customer of an investor owned utility. A utility may not require additional equipment or insurance or impose any other fee or requirement unless it is specifically authorized under these rules.

  • No more than 25 kW residential
  • No additional equipment, insurance or fee unless specifically authorized by the rules
Commercial, up to 500 kW Size 25.001 to 500 kW

Not greater than 500 kilowatts for a commercial customer of an investor owned utility. At a rural cooperative or a municipal utility the ceiling is 50 kilowatts instead, one tenth of this figure.

  • No more than 500 kW commercial at an investor owned utility
Industrial, up to 2 MW Size 500.001 to 2000 kW

Not greater than two megawatts for an industrial customer of an investor owned utility.

  • No more than 2 MW industrial at an investor owned utility

The screens that decide it

Ask the utility this, before you sell it

  1. Is this address served by an investor owned utility, a rural cooperative or a municipal utility? The size ceiling is 500 kilowatts commercial at an investor owned utility and 50 kilowatts at a cooperative or municipal, a tenfold difference.
  2. Is the service single phase or three phase? The penetration screen is 15 percent on three phase and only 5 percent on single phase.
  3. Please send Form No. 2, the interconnection standards and technical requirements incorporated by reference. The Secretary of State copy is a scan with no text layer, so the fee schedule, timelines, storage provisions and any insurance amounts cannot be read from the published rule.
  4. How much of the 3 percent aggregate cap remains, and how much of the half percent residential reserve?

Worth knowing before you quote

The rule body is deliberately thin: it obliges the utility to interconnect and defers the substance to Form No. 2. Section 3.7 is a conditional prohibition rather than an absolute one, barring a utility from requiring additional equipment or insurance or imposing any other fee unless specifically authorized under the rules, and no dollar amount appears anywhere in the readable text. Timelines, storage and non export provisions are unknown rather than absent, because they may sit in the unread form.

Source

West Virginia Code of State Rules 150-33, rules governing electric utility net metering arrangements and interconnections, effective 15 November 2019, with West Virginia Code 24-2F-8

Read and recorded 2026-09-12. Reaches investor owned utilities, rural electric cooperatives and municipally owned utilities, but with sharply different size limits. The interconnection detail is incorporated by reference as Form No. 2, and the authoritative copy on the Secretary of State site is a scanned image with no text layer, so the fee schedule, timelines, storage provisions and any insurance amounts could not be read.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.