Rules by state · Washington

Seattle City Light distributed energy resources

Their own published program, read and recorded. This outranks the Washington state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

the rated capacity of the resource in AC, which for an inverter based resource is the combined rated capacity in AC of the inverters that are part of it. This is the cleanest definition among the large publicly owned utilities, and Seattle applies the same one to both the interconnection level and net metering eligibility. One test, one number.

Size bands and what each one obliges

Level 1, standalone solar under 12 kW on the looped radial system Size 0 to 11.999 kW

No application fee. No insurance is required at or below 100 kW, and Seattle states outright that no interconnection customer is required to carry general liability insurance at that size. Screen result within 15 business days of the application being deemed complete.

  • Safety disconnect switch per Construction Standard 0097.03, shown on the site plan
  • UL 1741 SB and IEEE 1547-2018 certification
Level 2, solar 12 kW to 100 kW, any resource to 100 kW, or solar of any size on the network Size 12 to 100 kW

No application fee. Screen result within 20 business days. Resources on the network system must be non exporting and install specific equipment.

  • Safety disconnect switch
  • Non export scheme if on the network system
Level 3, inverter based above 100 kW to 500 kW Size 100.001 to 500 kW

An application fee applies at this level, set in the underlying policy rather than the handbook. Insurance of $1,000,000 is required above 100 kW up to 2 MW. Net metering no longer applies; the Large Customer Renewable Generation Program does.

  • Application fee per the underlying distribution policy
  • $1,000,000 liability insurance
Level 4, above 500 kW, machine based, or failing supplemental screens Size 500.001 to 20000 kW

Insurance is $2,000,000 above 2 MW to 5 MW and $3,000,000 above 5 MW to 20 MW. Above 5 MW there is no Seattle program compensating exports at all.

  • Application fee per the underlying distribution policy
  • Liability insurance by band

The screens that decide it

Ask the utility this, before you sell it

  1. Is there twelve months of minimum load data for this feeder? Which screen applies turns on the answer, and the fifteen percent fallback is the stricter one.
  2. What is the current queue position and has any upstream applicant withdrawn? Queue position decides who pays for system upgrades, and a withdrawal ahead of you can trigger re evaluation and change your cost.
  3. What are the Level 3 and Level 4 application fees? The handbook confirms they exist and points to the underlying distribution policy rather than stating them.

Worth knowing before you quote

Seattle City Light does not issue pre application reports on conditions at a point of common coupling, so a site cannot be pre screened. A safety disconnect switch is required on every system at any size under Washington worker safety law. Any change to resource type, location or nameplate capacity after queue assignment forfeits the queue position and requires a new application, so a redesign is not a revision. Downtown network customers cannot export at all. On the looped radial system a non export scheme may be a certified power control system, a nameplate no greater than 50 percent of the host facility minimum load over the past twelve months, or a reverse power flow relay. Net metering credits are valued at the retail rate, accrue from 1 April to 31 March, and are cleared out on 31 March under RCW 80.60.030. Published clocks are all in business days: completeness 10, Level 1 screen 15, Level 2 screen 20, agreement sent 5, applicant returns 10, countersigned agreement and permission to construct 5.

Source

Seattle City Light Distributed Energy Resources Interconnection Handbook, 2026 Edition, with Seattle Municipal Code 21.49.082 and 21.49.083 and Construction Standard 0097.03

Read and recorded 2026-09-12. Publicly owned utility, outside its state's interconnection rule. Its own published documents govern. Washington RCW 80.60 does bind Seattle City Light for net metering, which is where the 100 kW eligibility line and the 31 March credit reset come from. Interconnection terms are the utility’s own.

All Washington interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.