Memphis Light, Gas and Water distributed generation

Their own published program, read and recorded. This outranks the Tennessee state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

the proposed generation capacity in kW DC, applied with no conversion factor. The application collects kW DC, kVA and AC volts, and collects no AC kilowatt figure at all. The per kilowatt application fee is charged on a kilowatt the documents never identify, so the DC figure is used here because it is the larger one and quoting the smaller would understate the fee.

The screens that decide it

Ask the utility this, before you sell it

  1. Which kilowatt figure does the $5 per kW application fee use, the DC nameplate or the inverter kVA? The documents collect both and define neither.
  2. Is this address served by the downtown or medical center underground network? Distributed generation cannot be interconnected there at all, and the customer must instead interconnect to above ground standard distribution lines in the area.
  3. Does this site have three phase service? If Memphis Light, Gas and Water provides three phase, the project must use three phases of generation.
  4. What is the monthly electric service availability charge under options A and C? It is referenced but the amount lives in the Service Policy Manual.

Worth knowing before you quote

There is no net metering and no maximum system size published on any basis. There are no tiers, no review levels, no percentage caps and no screens of any kind, all confirmed by reading four documents in full. Insurance is required on every interconnection regardless of size, which is unusual: an original certificate from a company with an A.M. Best rating of no less than A:IX, at not less than $300,000 bodily injury per person, $700,000 for all persons in one occurrence, and $250,000 property damage. Export pays nothing on plain self generation; to be paid, the customer must sign a separate five year dispersed power production agreement with the Tennessee Valley Authority at avoided cost, paid by direct deposit from TVA rather than by the utility. All options require a separate generation meter. Published estimates are in calendar weeks: 4 to 5 weeks for technical review and 4 to 8 weeks for the construction cost quote. A failed acceptance test, including one failed for an incomplete installation, costs $200 and restarts scheduling. The contractor must collect the generation meter socket in person from the Electric Meter Shop on weekdays between 7:00am and 2:30pm. Micro inverter systems require a fused AC disconnect. Number 6 AWG or larger wire is required at the meter. Where the 2017 procedures and the 2025 overview conflict, the Service Policy Manual prevails, and neither document reproduces it.

Source

Memphis Light, Gas and Water Distributed Generation Process Overview updated 5 May 2025, with the Distributed Generation Interconnection Procedures of January 2017, the Application for Interconnection dated 1 September 2023 and the sample Interconnection and Parallel Operations Agreement of April 2016

Read and recorded 2026-09-12. Publicly owned utility, outside its state's interconnection rule. Its own published documents govern. Tennessee has no statewide interconnection standard. Memphis Light, Gas and Water is a local power company buying wholesale from the Tennessee Valley Authority, and has no net metering and no export compensation of its own.

All Tennessee interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.