Rules by state

Solar and battery interconnection rules in South Dakota

South Dakota small generator facility interconnection. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities. A utility outside that list sets its own terms, so confirm who serves the address first.

Check a South Dakota address free
How the size is measured

electric nameplate capacity: the net maximum electric output capability in watts, kilowatts or megawatts as designated by the manufacturer. The rule does not distinguish alternating from direct current. Note also that the fee formula uses a different term, rated generation output, which the chapter never defines, so a fee estimate should be flagged rather than presented as exact.

Size bands and what each one obliges

Tier 1 Size 0 to 10 kW

An inverter based facility of 10 kilowatts or less using lab tested equipment, not interconnecting to a transmission line. The application fee is $50. Insurance at this tier is proof of adequate homeowners, general liability or commercial liability cover sufficient for the size of the facility, with no dollar figure set.

  • $50 non refundable application fee
  • Lab tested inverter based equipment
  • Proof of adequate homeowners or general liability insurance, no amount specified
Tier 2 Size 10.001 to 2000 kW

Up to 2 megawatts on a radial or single premise spot network circuit using lab or field tested equipment. The fee is $50 plus $1 per kilowatt of rated generation output, capped at $500. Insurance is proof of cover up to a maximum of $500,000 at the utility request.

  • $50 plus $1 per kilowatt, capped at $500
  • Insurance up to $500,000 at utility request
Tier 4 Size 2000.001 to 10000 kW

Anything not qualifying for the lower tiers, up to 10 megawatts. The fee is $100 plus $2 per kilowatt, capped at $1,000, plus a study deposit. Insurance is proof of cover up to a maximum of $1,000,000 at the utility request. The utility may not impose additional requirements at this tier.

  • $100 plus $2 per kilowatt, capped at $1,000
  • System impact study agreement and deposit within 60 calendar days
  • Insurance up to $1,000,000 at utility request

The screens that decide it

Ask the utility this, before you sell it

  1. South Dakota has no net metering program at all, so what will you pay for exported energy? The interconnection chapter creates a right to connect and no billing credit, which is a different thing from a program that is closed.
  2. Is this address served by a municipal utility or a rural electric cooperative? Neither is a public utility under the statute and this chapter does not reach them.
  3. Is this project non export? Tier 3 covers a non export facility up to 2 megawatts and switches off the 15 percent screen entirely.

Worth knowing before you quote

Timelines are in business days unless noted: three to acknowledge receipt and state the review start date, ten to say whether the application is complete, fifteen to complete a Tier 1 review, twenty for Tiers 2 and 3, twenty five calendar days for an area network study, and ten to conduct a witness test, after which the customer may proceed if the utility has not. Before any cost above the application fee is assessed the applicant must authorize the utility to continue, or the application is considered withdrawn and the original fee forfeited. Self insurance is permitted. No aggregate cap exists because there is no program to cap.

Source

South Dakota Administrative Rules Chapter 20:10:36, small generator facility interconnection, effective 1 July 2009

Read and recorded 2026-09-12. Binds a public utility, and the statutory definition excludes utilities owned by municipalities, political subdivisions, state agencies and rural electric cooperatives, so this reaches the investor owned utilities only. South Dakota is also the state with a complete four tier interconnection standard and no net metering program of any kind: the chapter contains no billing credit mechanism and no export compensation, which is a finding rather than an omission.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.