Rules by state · South Carolina

Berkeley Electric Cooperative member owned solar

Their own published program, read and recorded. This outranks the South Carolina state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

the AC rating in kW. Berkeley states both program limits in kWAC and publishes an explicit sizing formula in AC kilowatts, which makes it unambiguous.

Size bands and what each one obliges

Residential, up to 20 kWAC Size 0 to 20 kW

A $150 one time interconnection fee is due before processing, plus $50 per field inspection. A copy of the homeowners insurance declaration must be submitted; no dollar amount of coverage is published. Exported energy is credited at 6.03 cents per kWh, updated each year around 1 March.

  • $150 interconnection fee before processing
  • $50 per field inspection
  • Copy of the homeowners insurance declaration page
  • A non demand, non time of day rate
Small commercial, up to 100 kWAC Size 20.001 to 100 kW

Available where the account transformer is under 100 kVa. Accounts over 100 kVa may install larger systems but receive no surplus credit value.

  • $150 interconnection fee before processing
  • $50 per field inspection
  • Transformer under 100 kVa for surplus credit eligibility

The screens that decide it

Ask the utility this, before you sell it

  1. What insurance amount is actually required? Berkeley asks for the homeowners insurance declaration page but publishes no minimum coverage figure.
  2. What screens and review timeline apply? The interconnection standard is published only as an unreadable image scan.
  3. Is this account on a time of day or demand billed rate? The program requires a non demand billed rate, which is a disqualifier to check before the sale, not after.

Worth knowing before you quote

The only published timeline is roughly two weeks, in calendar days, from the building code official releasing the job to the bidirectional meter being installed. There is no published approval clock. A meter tampering charge of up to $1,000 applies.

Source

Berkeley Electric Cooperative published solar and renewable energy program terms, with the Standard for Interconnecting Distributed Resources Up to 500 KVA

Read and recorded 2026-09-12. Rural electric cooperative, outside the South Carolina interconnection standard. The cooperative's own published documents govern. The 0421 interconnection standard is published only as an image scan with no text layer, so its tiers, insurance amounts, screens and timelines have not been read. Everything recorded here comes from the program pages.

All South Carolina interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.