Eugene Water and Electric Board customer generation

Their own published program, read and recorded. This outranks the Oregon state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

the AC output in kW. Every threshold in the standard and in the program terms is written in AC output, including the scope of less than 200 kW output, the 25 kW AC net metering ceiling, the 200 kW AC direct generation ceiling and the disconnect exemption. There are no kVA or DC terms anywhere in the standard, which makes this one of the cleanest AC bases in the platform.

Size bands and what each one obliges

Net metered, up to 25 kW AC output Size 0 to 25 kW

No application fee and no insurance are published at any size, both confirmed by reading the standard in full. The disconnect switch may be omitted only if all three conditions hold: the system is inverter based and UL 1741 certified for anti islanding, AC output is 25 kW or less, and service is under 600 volts on a self contained meter.

  • Customer obtains all electrical and other permits
  • Five working days notice before testing and before initial startup
  • Written EWEB approval before commencing interconnected operation
Direct generation, above 25 kW to 200 kW AC output Size 25.001 to 200 kW

Direct generation takes a separate service and meter. A disconnect switch is required. Above 200 kW output, applications are considered case by case.

  • Separate service and meter
  • Disconnect switch within five feet of the EWEB meter, NEMA 3R, true visible open
  • Double hasp shared lock, customer padlock and EWEB padlock

The screens that decide it

Ask the utility this, before you sell it

  1. Is this service current transformer metered? If so the disconnect switch is required no matter how small the system is.
  2. Is this address on the secondary network? If so the 25 percent of minimum load cap and the annual functional testing obligation both apply.
  3. How long will review and permission to operate take? No approval timeline is published; the only published day counts are five working days of notice the customer owes EWEB.

Worth knowing before you quote

Excess generation is trued up monthly and does not roll over to subsequent months. An annual offset savings model is therefore wrong at EWEB by a wide margin, because summer overproduction is worth far less than at a utility that nets annually. No percentage of consumption cap and no aggregate program cap are published. The standard has no battery clause; the contractor program page states that a paired battery should never be able to dispatch onto the distribution system, so treat storage as effectively non export here. On network installations the controls must be functionally tested annually for the life of the facility and the results submitted, which is an ongoing operating cost. Where required, the disconnect must give a true visible open with no components obscured by the switch case or an arc shield, and engraved laminated nameplates with specified wording are required. Incentive payment runs roughly four to six weeks from EWEB approval. The residential program has the customer submitting the application and bids, so do not assume installer submission.

Source

Eugene Water and Electric Board standard EC5-A.8000, Interconnection Requirements for Customer Generation Facilities of Less Than 200 kW, approved 13 July 2015, revision 1

Read and recorded 2026-09-12. Municipal or public utility, outside its state's interconnection rule. Its own published documents govern. An Oregon consumer owned utility, outside the Public Utility Commission interconnection rules. The standard predates storage and has no battery clause.

All Oregon interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.