Solar and battery interconnection rules in New Mexico

New Mexico interconnection of generating facilities. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities, electric cooperatives. A utility outside that list sets its own terms, so confirm who serves the address first.

Check a New Mexico address free
How the size is measured

rated capacity: the total AC nameplate rating of the power conversion units at the point of common coupling. New Mexico also defines nameplate rating, the sum of manufacturer maximum rated output regardless of limiting, and export capacity, which is the nameplate rating or a lower limited amount. Tier eligibility turns on nameplate rating while the review screens use export capacity.

Size bands and what each one obliges

Simplified Size 0 to 25 kW

A certified inverter based facility whose nameplate rating does not exceed 50 kW and whose export capacity does not exceed 25 kW. Both tests must pass. The screen places this tier at 25 kW because a system with no stated export limit exports everything it makes; a deliberately export limited design may reach the higher nameplate allowance. The application fee is $150 at 25 kW or less.

  • $150 application fee
  • Certified inverter based equipment
  • Nameplate rating not above 50 kW as well as export capacity not above 25 kW
Fast track Size 25.001 to 5000 kW

Up to 5 MW nameplate, with eligibility set by line voltage and distance from the substation. The fee is $300 between 25 and 100 kW, and $300 plus $1 per kW above 100 kW.

  • $300 application fee, plus $1 per kW above 100 kW
Detailed study Size 5000.001 to 10000 kW

Up to 10 MW rated capacity where the smaller processes do not apply. Above 10 MW the case specific rule at 17.9.569 governs instead.

  • Detailed study
  • $300 plus $1 per kW application fee

The screens that decide it

Ask the utility this, before you sell it

  1. What is the line voltage at this address, is this a mainline, and is the site within 2.5 miles of the substation? New Mexico fast track eligibility turns on all three.
  2. What is the relevant minimum load on this circuit? The screen is 100 percent of it and only the utility holds the figure.
  3. For a small utility, what consultant review costs will be charged above 10 kW? The rule permits recovery of reasonable consultant costs.

Worth knowing before you quote

New Mexico separates three quantities and a screening tool needs all of them: nameplate rating for tier eligibility, export capacity for the screens, and rated capacity as the AC figure at the point of common coupling. It also requires physical relabeling where a system is derated, by nameplate replacement or a supplemental adhesive derating tag. A non export facility pays $150 below 100 kW and $300 above it. The net metering tariff rule at 17.9.570 was not read, so any aggregate cap there is unknown.

Source

New Mexico Administrative Code 17.9.568, Interconnection of Generating Facilities With a Nameplate Rating Up To and Including 10 MW, replaced 14 February 2023

Read and recorded 2026-09-12. Applies to every electric utility including rural electric cooperatives and investor owned utilities subject to Public Regulation Commission jurisdiction. Municipal utilities are not named and remain outside it.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.