Solar and battery interconnection rules in Montana

Montana small generator interconnection. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities. A utility outside that list sets its own terms, so confirm who serves the address first.

Check a Montana address free
How the size is measured: not published

The published limits here are stated in kilowatts without saying whether that is the inverter rating in alternating current or the array rating in direct current. On a system near a threshold that decides which band it lands in, so the checker asks the question rather than choosing an answer.

Size bands and what each one obliges

Level 1 Size 0 to 10 kW

A nameplate capacity of 10 kW or less with certified equipment. Montana publishes no fee amounts and no insurance requirement at any level; each utility files a fee schedule and study rates with the Commission after public notice.

  • Certified equipment
  • Fee per the utility filed schedule
  • No insurance published in the rule
Level 2 Size 10.001 to 2000 kW

A nameplate capacity of 2 MW or less with certified equipment.

  • Certified equipment
  • Fee per the utility filed schedule
Level 4 Size 2000.001 to 10000 kW

Anything that does not meet the criteria for expedited review under the lower levels, up to the 10 MW aggregate nameplate ceiling of the rules.

  • Study process
  • Fee per the utility filed schedule

The screens that decide it

Ask the utility this, before you sell it

  1. Is this address served by a rural electric cooperative? Montana net metering does not apply to them at all, by an applicability section that says so in one sentence.
  2. What is your filed schedule of interconnection processing fees and study rates? Montana requires each utility to file one with the Commission and publishes no amounts itself.
  3. What is the line section annual peak load and the annual minimum load? Montana names both in the same screen.

Worth knowing before you quote

Montana publishes no insurance requirement and no prohibition, and no aggregate net metering cap of any kind, both confirmed by reading the rules and all five statute sections. Storage sits inside the definition of a small generator facility, which covers production, or storage and production, or storage alone. Level 3 is the non export track, up to 10 MW aggregate on a radial circuit and 50 kW on an area network, using reverse power relays or other protection that prevents export. Timelines are in business days: ten for completeness, fifteen more to verify, five to issue an agreement, thirty for the customer to sign, and twenty five for an area network impact study.

Utility programs we have read in Montana

Source

Montana Administrative Rules 38.5.8401 through 38.5.8413, small generator interconnection, effective 13 August 2010, with Montana Code Annotated 69-8-601 through 69-8-605

Read and recorded 2026-09-12. Binds an electric distribution company, defined as an electric utility distributing within Montana and subject to Commission regulation, so investor owned utilities only. The net metering statute is blunter still: its applicability section reads in full that the part does not apply to corporations organized under Title 35 chapter 18, which are the rural electric cooperatives. Montana cooperatives are outside net metering entirely.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities