Rules by state

Solar and battery interconnection rules in Mississippi

Mississippi distributed generator interconnection and net metering rules. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities. A utility outside that list sets its own terms, so confirm who serves the address first.

Check a Mississippi address free
How the size is measured

net metering nameplate direct current capacity of the aggregated facilities at the customer premises. Mississippi is the only southeastern state that sizes net metering eligibility on the direct current array rating rather than the inverter, so the panels decide whether the customer qualifies. The separate interconnection tier definition is stated as manufacturer maximum rated output without naming alternating or direct current, so the two tests in the same rule may not use the same number.

Size bands and what each one obliges

Level 1 Size 0 to 20 kW

An inverter based facility of 20 kW or less using certified equipment. A utility may not charge any application or other fee for a Level 1 review, the cheapest small application found in the southeastern states. The application form states the customer is not required to obtain general liability insurance coverage, and no external isolation device is required at this level.

  • No application fee
  • Certified inverter based equipment
  • No general liability insurance required
Level 2 Size 20.001 to 2000 kW

A nameplate capacity of 2 MW or less with certified equipment where aggregate generation on the circuit including this facility is 2 MW or less. Fees may reach $50 plus $1 per kilowatt plus the reasonable cost of minor modifications, with engineering at no more than $100 per hour. An external isolation device is required.

  • Up to $50 plus $1 per kilowatt
  • External isolation device
  • Engineering at no more than $100 per hour
Level 3 Size 2000.001 kW and above

Review by customer election or where the lower levels do not apply. Fees may reach $100 plus $2 per kilowatt plus actual time on impact or facilities studies at no more than $100 per hour.

  • Up to $100 plus $2 per kilowatt
  • Impact or facilities studies
  • External isolation device

The screens that decide it

Ask the utility this, before you sell it

  1. Is the residential net metering limit 10 kW or 20 kW of direct current capacity for this application? The published rule and a 2022 order sequence disagree and the Commission clean posting is an unreadable scan.
  2. How much of the aggregate cap remains? Mississippi allows a utility to refuse additional net metering requests once total net metering direct current capacity exceeds three percent of its peak demand recorded during the prior calendar year, and one version narrows the denominator to distribution system peak, which would make the cap smaller.
  3. Confirm the direct current array rating you will use to size this customer. Mississippi counts the panels, not the inverter, so a system that qualifies in the Carolinas may not qualify here.

Worth knowing before you quote

Mississippi publishes no insurance amounts at Level 2 or Level 3 and affirmatively disclaims a Level 1 requirement in the rule own form, which is the clearest statement of no insurance found in the region. It publishes no storage provision, no export limiting and no non export operating mode. Fees must be published on each utility website.

Source

Mississippi Distributed Generator Interconnection Rules and Renewable Energy Net Metering Rules, Mississippi Public Service Commission

Read and recorded 2026-09-12. Binds Commission jurisdictional electric utilities. Municipals and cooperatives are outside them. Note that the operative version of the residential net metering limit and the aggregate cap denominator turn on which 2022 order is in force; the Commission clean posting is a scanned image with no text layer, so both carry a version question.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.