Solar and battery interconnection rules in Maine

Maine small generator interconnection procedures. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities, municipal utilities, electric cooperatives.

Check a Maine address free
How the size is measured

generating capacity: the nameplate rating of the generator, and where the generator is direct current it is measured on the alternating current ratings of the proposed inverters. For photovoltaic this is the inverter AC rating, and it sets both the review level and the insurance band.

Size bands and what each one obliges

Level 1 Size 0 to 25 kW

An inverter based generator not greater than 25 kW. The application fee is $100 and a cost sharing fee of $150 is due when the executed agreement is returned. The customer is responsible for distribution upgrade costs above $5,000. No insurance is required for an inverter based facility of 1 MW or less.

  • $100 application fee
  • $150 cost sharing fee with the executed agreement
  • Distribution upgrade costs above $5,000
  • No insurance for inverter based at or below 1 MW
Level 2 Size 25.001 to 2000 kW

A generator not greater than 2 MW. The fee is $100 plus $2 per kW of generator capacity. For an on site load facility above 25 kW to 250 kW the cost sharing fee is $25 per kW and the customer carries distribution upgrade costs above $10,000.

  • $100 plus $2 per kW
  • Cost sharing of $25 per kW for on site load facilities above 25 kW to 250 kW
Level 4 Size 2000.001 kW and above

All generators not subject to federal jurisdiction that do not fit a lower level. The fee is $3,000 plus charges for actual study time, and a further $500 for changes to the application after notice of completeness. Insurance for an inverter based facility is $1,000,000 above 1 MW to 5 MW and $2,000,000 above 5 MW.

  • $3,000 application fee plus actual study time
  • $500 change fee after notice of completeness
  • $1,000,000 insurance above 1 MW to 5 MW, $2,000,000 above 5 MW

The screens that decide it

Ask the utility this, before you sell it

  1. What is the line section minimum load and minimum daytime load, and what percentage of it would this facility represent? Maine requires the utility to disclose all three on a screen failure where available, which is a better starting point than most states give.
  2. What is the export capacity of this design as you will record it? Maine measures the screens on export capacity and the insurance and review level on generating capacity, so an export limited system is measured two different ways at once.
  3. Is this address served by a consumer owned utility or a cooperative? Unlike most states these rules reach them, because the definition turns on operating a transmission and distribution plant rather than on ownership.

Worth knowing before you quote

Maine bars a utility from requiring an applicant to install additional controls including a utility accessible disconnect switch, to perform or pay for additional tests, or to buy additional liability insurance beyond the published table. That disconnect prohibition is a direct contrast with Wyoming and Arkansas, which mandate one. Level 3 is the non export track for generators not greater than 10 MW and is not a size band, with a fee of $100 plus $3 per kW. There is a dedicated energy storage section requiring a standard form describing the configuration, and a dedicated export control section listing the acceptable methods. Timelines run in business days: five to completeness, ten to screen results, ten for an additional review estimate, forty five for an impact study or thirty where a feasibility study was done, and ten to issue an agreement. No aggregate cap appears in the chapter.

Source

Maine Public Utilities Commission Chapter 324, small generator interconnection procedures, 65-407 CMR 324, filing 2023-233 from Docket 2023-00103

Read and recorded 2026-09-12. The applicability definition is entity neutral: a transmission and distribution utility is anyone owning, controlling, operating or managing a transmission and distribution plant for compensation in the state. It turns on operating the plant rather than on ownership form, so Maine consumer owned utilities and cooperatives are reached, unlike most states. Net energy billing sits in a separate chapter that was not read, so its size and consumption limits are unknown.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.