Solar and battery interconnection rules in Kentucky

Kentucky interconnection and net metering guidelines. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities, electric cooperatives. A utility outside that list sets its own terms, so confirm who serves the address first.

Check a Kentucky address free
How the size is measured: not published

The published limits here are stated in kilowatts without saying whether that is the inverter rating in alternating current or the array rating in direct current. On a system near a threshold that decides which band it lands in, so the checker asks the question rather than choosing an answer.

Size bands and what each one obliges

Level 1 Size 0 to 45 kW

Level 1 is defined by equipment rather than by size: an inverter based facility certified to UL 1741 by a nationally recognized testing laboratory, that also passes the Level 1 screens. No application, review, study, inspection or witness test fee may be charged for a Level 1 application.

  • UL 1741 certified inverter based equipment
  • No fees of any kind at Level 1
  • General liability insurance, which a standard homeowner policy may satisfy

The screens that decide it

Ask the utility this, before you sell it

  1. How much of the one percent cap remains on this supplier? Kentucky offers net metering first come first served up to one percent of the supplier single hour peak load in the previous year, and once that is reached the supplier has no further obligation to offer net metering to any new customer at any subsequent time. It is permanent once tripped, which makes it the most consequential cap of any state read.
  2. Is the 45 kilowatt limit measured in alternating or direct current? The statute says rated capacity and does not define it.
  3. Is this address served by a municipal utility? Neither statute section addresses municipals and the position is unresolved.

Worth knowing before you quote

Kentucky requires general liability insurance at both levels, which a standard homeowner, commercial or other policy may satisfy, and states no dollar amount. A Level 2 application is required where the facility is not inverter based, the equipment is not UL 1741 certified, or a Level 1 condition is not met; it carries a non refundable fee of up to $100 and up to $1,000 for an initial impact study. Level 1 is decided within 20 business days and Level 2 within 30. The customer notifies the utility within three business days of completion and the witness test occurs within ten. There is no minimum load screen and no storage or non export provision; the guidelines predate storage.

Source

Kentucky Public Service Commission interconnection and net metering guidelines, Appendix A to Administrative Case 2008-00169, with KRS 278.465 and 278.466

Read and recorded 2026-09-12. Applies to every retail electric supplier in the Commonwealth, and Kentucky distribution cooperatives are Commission jurisdictional and covered. Municipal applicability is not addressed in either statute section and is unresolved. The guidelines document still states the superseded 30 kW eligibility limit; Senate Bill 100 of 2019 raised it to 45 kW, so the statute governs size and the guidelines govern process.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.