City Water, Light and Power Springfield solar interconnection

Their own published program, read and recorded. This outranks the Illinois state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured: not published

The published limits here are stated in kilowatts without saying whether that is the inverter rating in alternating current or the array rating in direct current. On a system near a threshold that decides which band it lands in, so the checker asks the question rather than choosing an answer.

Size bands and what each one obliges

Under 25, on the standard packet Size 0 to 25 kW

A $400 check is due with the packet, itemized as a $50 application fee, $150 net meter, $50 interconnection testing and $150 installation of two meters. The check is held until the meters are installed. No insurance is required.

  • $400 check with the application packet
  • Customer furnishes both meter sockets from the approved list, a NEMA 3R fused disconnect, tap connectors, conduit and all wiring
  • Lockable exterior fused disconnect
Over 25, engineering review and line side connection Size 25.001 to 2500 kW

An additional $300 engineering review fee is due with the packet, and the solar circuit must be connected to the line side of the revenue meter, which is a materially more expensive service rework than a load side backfeed breaker. The transmission and distribution engineering department reviews and approves the installation.

  • $300 engineering review fee with the packet
  • Line side connection to the revenue meter
  • Transmission and distribution engineering approval

The screens that decide it

Ask the utility this, before you sell it

  1. Is the 25 threshold measured on inverter AC, on the DC array, or in kVA? The packet says all three and the data sheet the utility reads collects only the DC array size.
  2. How long will review take? No approval timeline is published; the only published duration is two weeks to install the two meters after the check is processed.
  3. Does this site have three phase service? A three phase service requires a three phase generator.
  4. If the solar circuit lands inside the billing meter base, coordination with the maintenance supervisor is required at least one week ahead. Is that needed here?

Worth knowing before you quote

Net metering is open and is full retail while it lasts, but the credit is confiscated rather than paid: on the 1 March billing cycle reconciliation, or on closing the account, the customer surrenders any excess energy, and under no circumstances are there payments or credit transfers. The contract also says outright that there is no guarantee of net metering in perpetuity. No insurance is required and liability is handled by a hold harmless clause alone. No aggregate program cap, no percentage of consumption cap, no fifteen percent screen and no minimum load test are published. The isolation device may be locked off by the utility during maintenance and may not be returned to the on position other than by an authorized city official. The contractor runs the whole process; the customer signs the interconnection agreement and the net meter contract.

Source

City Water, Light and Power Springfield Illinois Solar Application Packet revised 12 June 2023, containing the Solar Project Information Sheet, the Application for Interconnection, the Solar Data Sheet and the approved wiring diagrams, with the Net Metering Contract revised 12 June 2023

Read and recorded 2026-09-12. Municipal or public power utility, outside its state's interconnection rule. Its own published documents govern. An Illinois municipal utility. The Illinois Commerce Commission smart solar billing transition binds investor owned utilities and does not reach City Water, Light and Power, whose own documents still provide full retail netting.

All Illinois interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.