Rules by state

Solar and battery interconnection rules in Hawaii

Hawaii interconnection and Smart Renewable Energy Program. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities, electric cooperatives. A utility outside that list sets its own terms, so confirm who serves the address first.

Check a Hawaii address free
How the size is measured

program system size: the sum of all inverter strings, where each string is the lesser of its photovoltaic kW direct current capacity or its inverter kW alternating current capacity. Hawaii is the only state read that takes the smaller of the two per string and then sums, and program system size is what sets the insurance band. Technical system size goes further, taking the lesser of that figure or the maximum export permitted by an on site limiting element, and is used for the technical review.

Size bands and what each one obliges

Up to 16 kW Size 0 to 16 kW

A program system size of 16 kW or less is exempt from commercial general liability insurance. The application charge is $50 unless the application is submitted through the online customer interconnection tool, in which case there is none.

  • $50 application charge, waived if filed online
  • No commercial general liability policy required
Above 16 kW to 30 kW Size 16.001 to 30 kW

Commercial general liability insurance of $500,000 is required. A single phase facility above 10 kW is reviewed in the initial technical review rather than passing straight through.

  • $500,000 commercial general liability insurance
  • $50 application charge, waived if filed online
Above 30 kW to 250 kW Size 30.001 to 250 kW

Insurance rises to $1,000,000. A three line diagram is required at 30 kW and above.

  • $1,000,000 commercial general liability insurance
  • Three line diagram
Above 250 kW to 1 MW Size 250.001 to 1000 kW

Insurance rises to $2,000,000.

  • $2,000,000 commercial general liability insurance
Above 1 MW Size 1000.001 kW and above

Insurance rises to $5,000,000.

  • $5,000,000 commercial general liability insurance

The screens that decide it

Ask the utility this, before you sell it

  1. Confirm this customer is enrolling in the Smart Renewable Energy Program. Net energy metering, customer self supply, customer grid supply, customer grid supply plus and smart export are all closed to new enrollments, and net metering plus is open only to an existing net metering customer, so a new customer has one option.
  2. What is the interconnection requirements study cost estimate? Hawaii publishes no study deposit schedule and prices each study individually, and the customer either pays the estimate or withdraws.
  3. Is the battery discharge limited by programming or an on site limiting element? If so the reduced figure is used for technical system size, which can move the project into a lighter review.

Worth knowing before you quote

Note the conflict between the two Hawaiian Electric documents on insurance and use the program tariff: the interconnection standards say the company will not impose a standardized insurance requirement, while the Smart Renewable Energy Program tariff publishes a full table by capacity band. Timelines are in business days except the interconnection requirements study, which is 150 calendar days: five to provide standards, fifteen for completeness, fifteen for the initial technical review, twenty for supplemental review, then five and fifteen for the closing steps. No aggregate program cap appears in the Rule 32 tariff.

Source

Hawaiian Electric Rule 14 Paragraph H interconnection standards with Appendices I and III, and Rule 32 Smart Renewable Energy Program effective 1 April 2024, Docket 2019-0323

Read and recorded 2026-09-12. Hawaii regulates every electric utility including the Kauai cooperative, so the approved tariffs are effectively statewide, but only the Hawaiian Electric tariff was read. Which program is open matters more here than anywhere else: net energy metering closed as fully subscribed on 12 October 2015, and customer self supply, customer grid supply, customer grid supply plus and smart export all closed to new enrollments on 1 April 2024. Net energy metering plus is open only to existing net metering customers. The program a new customer can actually take today is Rule 32, the Smart Renewable Energy Program.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.