Rules by state · Florida

Ocala Electric Utility net metering

Their own published program, read and recorded. This outranks the Florida state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

gross power rating: the alternating current rating, which Ocala Electric Utility defines as 85 percent of the direct current rating. The AC rating determines the tier for agreement purposes, and the inverter nameplate does not enter into it.

Size bands and what each one obliges

Tier 1 Size 0 to 10 kW

No application fee. Insurance is required but the amount appears only in the unpublished interconnection agreement.

  • Interconnection agreement, obtained at an in person meeting
  • Proof of insurance for the tier
  • Maximum size letter from OEU before the building permit
Tier 2 Size 10.001 to 100 kW

An application fee applies. Ocala publishes the fee structure but not the dollar amount.

  • Application fee, amount not published
  • Proof of insurance for the tier
  • Maximum size letter from OEU before the building permit
Tier 3 Size 100.001 to 2000 kW

An application fee plus a study fee are due at submittal. The study fee is an estimate, only actual costs are charged against it, and the customer remains responsible for any final cost above the estimate.

  • Application fee, amount not published
  • Study fee at submittal, amount not published
  • Proof of insurance for the tier

The screens that decide it

Ask the utility this, before you sell it

  1. How much of the 2.5 percent aggregate peak demand cap is currently subscribed, and is the queue holding applications? Ocala publishes no tracker and this is the largest single risk to a sales pipeline here.
  2. What is the maximum allowable system size for this address? OEU calculates it from historical consumption and issues a letter that must accompany the building permit application.
  3. What is the application fee, the study fee and the insurance minimum at this tier? Ocala publishes the structure but no dollar amounts, which appear only in the agreement handed out at the in person meeting.
  4. For three phase service, what is the monthly cellular service charge and the special equipment fee for the required modem?

Worth knowing before you quote

Ocala caps the system at 100 percent of calculated annual consumption with no headroom, and the penalty for exceeding it is severe: the net meter is removed and the customer and service location are barred from the net metering program in future. The process also excludes installers. Ocala will no longer accept interconnection agreements submitted by contractors, installers or third party processors, the property owner must submit directly, an in person meeting with OEU comes before contractor engineering is submitted, and an OEU approval letter is required before the building permit can be pulled. Battery rules are fully published: storage paired with generation may not export, backup only storage with no generation needs no interconnection agreement but requires a listed automatic transfer switch, and grid interactive standalone storage is prohibited outright. A placard reading that battery storage is utilized in the facility must be permanently affixed to the meter enclosure.

Source

Ocala Electric Utility Net Metering Guidelines, revised 1 March 2022, and the Solar Net Metering FAQ

Read and recorded 2026-09-12. Municipal utility. Not bound by Florida Administrative Code Rule 25-6.065, which applies to investor owned utilities. Sets its own interconnection terms.

All Florida interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.