Rules by state · Florida

Kissimmee Utility Authority net metering

Their own published program, read and recorded. This outranks the Florida state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

gross power rating: the total manufacturer AC nameplate generating capacity, which for inverter based systems KUA calculates by multiplying the total installed DC nameplate generating capacity by 0.85.

Size bands and what each one obliges

Tier 1 Size 0 to 10 kW

No application fee. Insurance of $100,000 is encouraged but not required.

  • Interconnection application
  • No fee
  • Tri-Party agreement with FMPA
Tier 2 Size 10.001 to 100 kW

A $320 application fee applies and $1,000,000 general liability insurance is a requirement, not a recommendation.

  • $320 application fee
  • $1,000,000 general liability insurance
  • Tri-Party agreement with FMPA
Tier 3 Size 100.001 to 2000 kW

A $470 application fee applies, $2,000,000 insurance is a requirement, and the complete study fee must be deposited before study work begins. Studies by other engineering consultants are not accepted.

  • $470 application fee
  • $2,000,000 general liability insurance
  • Full study fee deposited before commencement
  • KUA engaged consultant only
  • Tri-Party agreement with FMPA

The screens that decide it

Ask the utility this, before you sell it

  1. What is the KUA distribution service rating at this address? The gross power rating must not exceed 90 percent of it.
  2. Confirm the Tri-Party Net Metering Purchase Power Agreement with FMPA is included. KUA is bound by the FMPA All-Requirements contract and cannot buy the excess itself, so this third signature is required and is the step installers most often miss.
  3. What is the current queue time? KUA executes within 30 calendar days of a completed application and issues permission to operate within 15 business days of documentation and the switch demonstration.

Worth knowing before you quote

KUA publishes no percentage of annual consumption cap and no aggregate program cap; it limits by the 90 percent service rating test instead. The executed agreement must be used within one year of KUA execution. Adding a second generation system requires 60 days advance written notice.

Source

Kissimmee Utility Authority Application for Interconnection packet, including the Tier agreement and the Tri-Party Net Metering Purchase Power Agreement

Read and recorded 2026-09-12. Municipal utility. Not bound by Florida Administrative Code Rule 25-6.065, which applies to investor owned utilities. Sets its own interconnection terms.

All Florida interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.