Florida Public Utilities Company renewable generation interconnection

Their own published program, read and recorded. This outranks the Florida state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

gross power rating: the total manufacturer AC nameplate generating capacity of the renewable generation system. For inverter based systems the AC nameplate generating capacity is calculated by multiplying the total installed DC nameplate generating capacity by 0.85 to account for losses during the conversion from DC to AC. The inverter own rating does not determine the tier, so sizing to the Tier 1 boundary means a DC ceiling of 11.764 kW.

Size bands and what each one obliges

Tier 1 Size 0 to 10 kW

No application fee and no insurance requirement.

  • Interconnection agreement, obtained at the local office
Tier 2 Size 10.001 to 100 kW

A $350 non refundable application fee applies and general liability insurance of $1,000,000 is required.

  • $350 non refundable application fee
  • $1,000,000 general liability insurance
Tier 3 Size 100.001 to 2000 kW

The same $350 non refundable application fee applies, making FPUC the cheapest Tier 3 application in Florida, and insurance of $2,000,000 is required. Where a study is required the customer pays $2,000 before it begins and is refunded the difference if the actual cost is lower.

  • $350 non refundable application fee
  • $2,000,000 general liability insurance
  • $2,000 study deposit where a study is required

The screens that decide it

Ask the utility this, before you sell it

  1. FPUC publishes no timelines of its own and defers to Rule 25-6.065. Confirm the current queue time at the local office.
  2. FPUC publishes nothing on battery storage. If a battery is included, confirm what is required.
  3. What is the utility distribution service rating at this address? The gross power rating may not exceed 90 percent of it under the governing rule.

Worth knowing before you quote

FPUC publishes no percentage of annual consumption test, no storage rules, no aggregate program cap and no timelines. Because it defers to Rule 25-6.065, the rule timelines govern by default: 10 business days to acknowledge or identify a deficiency, 30 calendar days to execute a completed application, and 90 days where a Tier 3 study is required. Agreements are obtained at the local office rather than online.

Source

Florida Public Utilities Company Renewable Generation Systems Application and solar interconnection page

Read and recorded 2026-09-12. Investor owned utility under Florida Public Service Commission jurisdiction. FPUC publishes no thresholds of its own beyond the rule and defers explicitly to Rule 25-6.065.

All Florida interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.