City of Tallahassee solar net metering

Their own published program, read and recorded. This outranks the Florida state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured

the array rating stated in kW AC. Tallahassee denominates its limits in kWac and publishes no DC to AC conversion factor.

Size bands and what each one obliges

Single phase, up to 15 kWac Size 0 to 15 kW

Single phase connections are permitted up to 15 kWac. General liability insurance of at least $100,000 is required, and in residential applications a standard homeowner policy at that amount may satisfy it.

  • Solar net metering agreement
  • $100,000 general liability insurance
Above 15 kWac, three phase required Size 15.001 to 100 kW

For power levels exceeding 15 kWac a three phase balanced interconnection is required. Insurance remains at least $100,000.

  • Solar net metering agreement
  • Three phase balanced interconnection
  • $100,000 general liability insurance

The screens that decide it

Ask the utility this, before you sell it

  1. Is the service at this address single phase or three phase? Above 15 kWac a three phase interconnection is required.
  2. Is there an application fee? None is published.
  3. How long does approval, inspection and meter set take? The City publishes no timeline at all.

Worth knowing before you quote

Tallahassee publishes no application fee, no percentage of consumption cap, no aggregate program cap, no storage provision and no timeline commitment. Credits carry forward on a rolling twelve month period and expire: in no event is the owner paid for excess energy at the end of that period. The City retains the renewable energy credits, which limits what a savings claim to a customer can say. Any modification to the system terminates the agreement and requires a new one.

Source

City of Tallahassee Solar Net Metering Agreement, residential, revision 5 dated 2 August 2019, and the Application for PV Systems up to 100 kWac

Read and recorded 2026-09-12. Municipal utility. Not bound by Florida Administrative Code Rule 25-6.065, which applies to investor owned utilities. Sets its own interconnection terms.

All Florida interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.