Central Florida Electric Cooperative small photovoltaic interconnection

Their own published program, read and recorded. This outranks the Florida state rule wherever the two differ, because it is the program this utility actually administers.

Check an address on this utility free
How the size is measured: not published

The published limits here are stated in kilowatts without saying whether that is the inverter rating in alternating current or the array rating in direct current. On a system near a threshold that decides which band it lands in, so the checker asks the question rather than choosing an answer.

Size bands and what each one obliges

Small photovoltaic system Size 0 to 1000 kW

CFEC publishes no tiers. Every system pays the same $100 interconnection fee and carries the same $100,000 liability insurance requirement with CFEC listed as an additional interest.

  • $100 interconnection fee
  • $100,000 personal injury and property damage liability insurance listing CFEC as additional interest
  • Insurance declaration page
  • FSEC Standard 203-05 approval
  • Lockable visible load break manual disconnect

The screens that decide it

Ask the utility this, before you sell it

  1. Is the 1,000 kW nameplate limit measured in AC or DC? CFEC does not say, and on a large system the answer changes whether the project qualifies.
  2. Confirm the equipment carries FSEC Standard 203-05 approval. CFEC requires it and no other Florida utility researched does.
  3. How long does review and meter set take? CFEC publishes no timeline.

Worth knowing before you quote

CFEC buys excess kilowatt hours at an avoided cost of 4.1 cents per kWh, subject to change. Insurance is required at every size, including the smallest residential system. CFEC publishes no consumption cap and no aggregate program cap.

Source

Central Florida Electric Cooperative Interconnection Requirement List and Interconnection Agreement

Read and recorded 2026-09-12. Rural electric cooperative. Not bound by the interconnection standards of Florida Administrative Code Rule 25-6.065, which applies to investor owned utilities; only the subsection (10) reporting obligation reaches cooperatives. CFEC publishes no tiers at all; one set of requirements covers every size.

All Florida interconnection rules

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.

How it works for utilities

Also from CivyxIQ, if they fit what you already do: SolarProjeX for running the crews and the jobs, and Solar Home so the homeowner can follow their own project. Neither is needed to use the checker.