Solar and battery interconnection rules in Connecticut

Connecticut generator interconnection guidelines. Every threshold below was read out of the document linked at the bottom of this page, and the same rules answer the free screening check.

Who this binds: investor owned utilities. A utility outside that list sets its own terms, so confirm who serves the address first.

Check a Connecticut address free
How the size is measured

the aggregate nameplate rating in kW AC at the site. Connecticut states the residential threshold as 20 kW AC and the incentive program measures the inverter nameplate capacity in kW AC, with no DC conversion factor anywhere.

Size bands and what each one obliges

Residential single phase, 20 kW AC or less Size 0 to 20 kW

Certified inverter based residential single phase interconnection at an aggregate nameplate rating of 20 kW AC or less. The application fee is $200 and no insurance is required at all. Approval follows within 10 business days.

  • $200 application fee
  • Certified inverter based equipment
  • No insurance required
Fast track Size 20.001 to 2000 kW

Up to two megawatts where the technical screens pass, or a certified system of 25 kW or less that failed the small system screen. The application fee is $500 and study costs are actual cost. Insurance is $300,000 at or below 100 kW and $1,000,000 above 100 kW to 1 MW.

  • $500 application fee
  • $300,000 insurance at or below 100 kW, $1,000,000 above it to 1 MW
Study process Size 2000.001 to 20000 kW

Larger than two megawatts, or two megawatts or less and uncertified, or certified but failed fast track. The application fee is $1,000 and study costs are actual cost. Insurance is $2,000,000 above 1 MW to 5 MW and $5,000,000 above 5 MW to 20 MW.

  • $1,000 application fee
  • $2,000,000 insurance above 1 MW to 5 MW, $5,000,000 above 5 MW

The screens that decide it

Ask the utility this, before you sell it

  1. Does this project include a battery? Connecticut counts additional AC capacity attributed to a storage system toward the interconnection application level even though it does not count toward the 25 kW AC incentive cap, so a 20 kW solar plus 10 kW battery job leaves the cheap residential lane and pays $500 instead of $200.
  2. A certified three phase system of about 22 kW falls between the residential guideline, which covers single phase at 20 kW AC, and the fast track guideline, which excludes inverter projects of 25 kW and less. Which process applies?
  3. What is this customer highest annual consumption over the past five years? The incentive program limits expected annual production to that figure plus five percent, plus an allowance for planned electric vehicles and a whole home heat pump.

Worth knowing before you quote

Connecticut requires no insurance at all for a residential system of 20 kW AC or less, which is stated plainly in the guidelines. Legacy net metering closed to applications submitted on or after 1 January 2022 and new customers take the Residential Renewable Energy Solutions tariff, which is rate set to a deployment target of 50 to 60 megawatts a year rather than a hard capacity cap. Connecticut uses 87.5 percent as the short circuit interrupting capability limit where Massachusetts uses 85 percent. The summary insurance table in the published fast track guideline is misaligned by one row in the source document; the prose governs.

Source

Connecticut guidelines for the interconnection of residential single phase certified inverter based generating facilities of 20 kW AC or less, PURA docket 03-01-15RE03, and the guidelines for generator interconnection fast track and study processes, PURA docket 17-12-03RE06 dated 20 December 2023

Read and recorded 2026-09-12. Issued jointly by Eversource and The United Illuminating Company and approved by the Public Utilities Regulatory Authority, so they are statewide uniform in substance. Connecticut municipal utilities are excluded by statutory definition: an electric distribution company does not include a municipal electric utility other than a participating one, so Wallingford, Norwich, Groton, South Norwalk and Jewett City are outside these guidelines.

What to do with this

Check a real address

The rules below are the general case. Run the free check to see which utility serves a specific address, which tier the system lands in, and what to ask.

Run the free check
Installers: keep the answer with the job

GridProjeX holds the project from here, with every value tied to the document it came from and the utility and permit tracks run to permission to operate.

How it works for installers
Utilities: see what applicants are told

The same published rules your applicants read here are the ones your queue sees. GridProjeX is the record both sides work from.